October 2024
We are excited to share a major milestone for The International, Brighton – the crane officially came down recently, bringing us one step closer to the finish line! With completion on track for early 2025, things are shaping up nicely.
The finishing touches are underway, and we can’t wait to share more with you soon! Stay tuned as we bring this vision to life.
Video credit: BOW Projects and Motion Media
March 2024
The majority of works that occurred in the month of February were internal fit-outs of both the apartments and amenities.
Carpet installation has progressed well to Level 2 and Level 3. Penthouses on Level 4 have had stone and timber floor nearing completion.
The common area, Wine room and Business suites have been fully fitted out as well.
Landscaping plants and irrigation have been installed on the Rooftop amenities and Terraces of the townhouses block.
January 2024
The works on site have restarted after a short break over the New Year.
Internally, Level 4 joinery and timber flooring are scheduled to be completed by mid-February. We have also commenced defects rectification for the Ground Floor and Level 1 apartments.
Externally, the GRC panels are being installed on Level 3 and Level 4 elevations. The Bay St elevation is scheduled for a late February installation. Landscaping has commenced on the rooftop terrace.
We are also in the process of obtaining Authority consent for the registration of the Titles.
Construction completion is currently programmed for April 2024.
November 2023
Construction completion is programmed for February 2024, with the internal defecting process now underway.
Internally, carpet has been installed on the Ground Floor and Level 1 apartments, which has enabled the apartments to be defected, cleaned and closed.
The installation of joinery and stone is complete to all Level 3 apartments, with timber flooring nearing completion and carpet installation to follow thereafter. Tiling and joinery installation is progressing on Level 4.
Externally, the GRC panels are predominately installed up to Level 2 with Level 3 underway.
October 2023
Construction completion is programmed for February 2024, with internal fit-out works to be completed by the end of the year allowing for a comprehensive quality control process.
Internally, the installation of joinery and stone is complete for all Level 2 apartments with timber flooring to follow.
Tiling and joinery works are progressing well on Level 3. Window glazing has progressed up to Level 4.
The frameless wall-to-ceiling glazing has also been installed throughout the ground floor amenities and the area has been prepared for tiling.
July 2023
Construction at The International is progressing steadily, with works occurring on all fronts. Internally, the installation of joinery and stone is complete for all Ground Floor apartments, with Levels 1 and 2 underway. Bathroom tiling has progressed up to Level 2, with plaster partitions now completed to Level 3.
We will see the bay windows glazed in the coming weeks, a signature design element of The International.
April 2023
Construction completion is progressing towards Q4 this year. See the video below for an insight into the façade panel and joinery manufacturing process.
January 2023
Ground floor and level 1 plastering, electrical, and mechanical works are either in the rough-in or fit-out stage. Level 2 and 3 are undergoing framing work.
December 2022
Topping out is now complete. Earlier in December we celebrated the topping out of The International, alongside builders VCON and the wider consultant team which included Carr, V-Leader, MaxCap and PDA Australia.
October 2022
The level 2 and level 3 southern slabs were poured in October. The final two remaining slabs will be poured in November, enabling the topping out of the structure.
Services works and blockwork wall works are progressing well in the basement levels, as the site opens further with the removal of back props.
September 2022
The level 4 slab has now been poured, giving a sense of the soaring Bay and city views that penthouse residents can expect. The rooftop slab, that sits above level 4, will be poured in the coming weeks and the precast structural columns are being installed on level 4. Basement fit-out works are well underway with the removal of propping opening up the spaces. The topping out of the structure will be our next milestone, which is on schedule for the end of the year.
July 2022
The building is now out of the ground and we are currently pouring the level two slab.
June 2022
The slabs for the two level basement have been poured and the crane has been installed. The building will now commence coming out of the ground with services rough-in and façade works to follow.
April 2022
Bulk excavation is now complete with the crane and concrete pump installed. VCON will complete basement 2 slab by mid-May with suspended basement 1 slab to follow thereafter.
February 2022
Basement 2 bulk excavation is nearing completion with concrete footings/slab to be poured by mid-March. VCON remains on programme. Crane installation is scheduled for the end of March. Local joinery manufacturers INDETAIL have been engaged. Click here to check out their work on Instagram.
January 2022
Shotcreting to Basement 1 has been finalised with Basement 2 bulk excavation underway.
December 2021
Demolition has now been finalised with piling and capping beam works nearing completion. Bulk excavation, ground anchor installation and shotcreting to basement walls will commence thereafter.